Robinson Playground
Start Date: 6/24/24 ~ Estimated Completion Date: 8/30/24
Project Overview: The hardtop playground is being replaced with an accessible play structure. The project involves removal of the existing asphalt, fence, and ball pit. There will be a lot of sitework to grade the playground area, and the installation of a retaining wall will take place. The new play structure will be accompanied by a shade structure to provide sun/heat relief to students. There will also be trees and shrubs added to beautify the area.
Before Pictures




Photos of the Project Progress